Middlesbrough roadworks report

A66 ROADWORKS

NORTH MIDDLESBROUGH ACCESSIBILITY SCHEME

Construction works have commenced on the proposed access road linking the A66/ Cannon Park Interchange with Riverside Park Road. Lane restrictions are currently in place during off-peak periods on the A66, between the A19 Interchange and Cannon Park Interchange. Delays are expected.

Further information will be available on www.northmiddlesbroughaccessibility.com

SLIP ROAD CLOSURE - CANNON PARK INTERCHANGE

The slip road from Cannon Park Interchange onto the A66 eastbound will be closed from Sunday 23rd November 2008 for approximately 4 months, to enable the progression of works associated with the North Middlesbrough Accessibility Scheme. Diversions will be via Newport Road and Hartington Interchange.

SLIP ROAD CLOSURE - HARTINGTON INTERCHANGE

The slip road from Hartington Interchange onto the A66 eastbound will be closed on Tuesday 18th November 2008 (one night only), from 07.30pm until approximately midnight, for the installation of high mast columns. Diversions will be signed via the A66 and Newport Interchange.

NEWPORT ROUNDABOUT

Lane closures on all approach roads to Newport Roundabout may be in place during off-peak periods until mid December 2008, as part of the NMA Scheme. Delays will be expected.

A66 MAINTENANCE WORKS

Lane closures are necessary each Sunday at various locations on the A66 for detailed inspection works, gully cleaning, repairs to street lighting and road sweeping. Washing of street sign name plates and direction signs to take place until further notice.

Maintenance works involving a near-side lane closure will take place on Sunday 16th November 2008, on the A66 westbound main carriageway from Hartington Interchange entry slip to A19 Interchange, also Hartington Interchange entry slip and Cannon Park Interchange entry and exit slips.

VARIOUS LOCATIONS

ACKLAM ROAD ROUNDABOUT

Lumsden and Carroll Construction Ltd, will continue works until January 2009 to construct a new roundabout on Acklam Road, at the junction of Springvale Terrace. Temporary traffic signals will be in operation until Christmas 2008.

ST. BARNABAS ROAD, LINTHORPE

A temporary road closure is in place at the junction with Linthorpe Road for NGN works. The works are expected to be complete by the end of November and the closure will be in place for the duration of the works.

LINTHORPE ROAD, BETWEEN ST. BARNABAS ROAD AND CLIVE ROAD

A lane closure will be in place at the above location from Monday 3rd November 2008, to allow mains renewal works by Northumbrian Water. The works have been programmed early to take advantage of the existing road closure at St Barnabas Road and they are expected to continue for 3 weeks.

THE AVENUE, LINTHORPE

The excavation of trial holes is ongoing at various locations, between the junctions with Orchard Road and Eastbourne Road.

BRIDGE STREET WEST

NEDL will be laying LV cables in the footpath between Sussex Street and Albert Street, until 03 December 2008.

BRIDGE STREET EAST - TEMPORARY ROAD CLOSURE

Works are continuing to reconstruct the carriageway and footways on Bridge Street East, from Queens Square to Gray Street. The development works will continue until December 2008 and although the road will be closed to vehicles, pedestrian access will be maintained throughout this period.

MARTON ROAD/ BROUGHTON AVENUE JUNCTION

Murphy's will continue cable diversion works for NEDL, until 15th December 2008, in the verge on Marton Road opposite the junction with Broughton Avenue.

CANNON STREET

NEDL cable diversion works are continuing outside Discount DIY until 27th November 2008.

STREET LIGHTING MAINTENANCE WORKS

The general maintenance of street lighting columns is continuously ongoing at various locations in Middlesbrough.

RESURFACING WORKS

LATHAM ROAD, LINTHORPE

Carriageway resurfacing works, involving a temporary road closure, are continuing at the above location.

LINTHORPE MEWS

Resurfacing works will take place on Saturday 15th November 2008, commencing 06.30pm until 08.00pm, to be complete early Sunday morning.

FOOTPATH WORKS

RAINSFORD CRESCENT

Works are ongoing to replace grass verges with tarmac, between no's 45-75.

MOORTOWN ROAD, BEECHWOOD

Works are ongoing to replace grass verges with paving at the above location.

MALLOWDALE, NUNTHORPE

Footpath resurfacing works are ongoing between Stainton Way and Clevegate.

MARTON ROAD

Footpath renewal works between St. Joseph's School and Belle Vue Grove Roundabout have been suspended until after the Christmas period.

We'd like to hear from you. Join us and send your stories and pictures.

Leave a comment


Type the characters you see in the picture above.

Latest news from all Teeside communities

Teeside by map View bigger map

Recent Comments

Archives

Local Jobs

Sponsored links