PROPOSED NORTH MIDDLESBROUGH ACCESSIBILITY SCHEME
Construction works have commenced on the proposed access road linking the A66/ Cannon Park Interchange with Riverside Park Road. Lane restrictions are currently in place during off-peak periods on the A66, between the A19 Interchange and Cannon Park Interchange. Delays are expected.
Further information will be available on www.northmiddlesbroughaccessibility.com
A66 HIGH MAST COLUMN INSTALLATION
Enabling works have commenced for the installation of high mast columns, on the A66 eastbound and westbound carriageways, between the A19 Interchange and Cargo Fleet Interchange. Off-peak lane closures will be in place as the works progress and delays may be expected.
A66 ROAD WORKS
Lane closures are necessary each Sunday at various locations on the A66 for detailed inspection works, gully cleaning, repairs to street lighting and road sweeping. Washing of street sign name plates and direction signs to take place until further notice.
Maintenance works involving a nearside lane closure will take place on Sunday 19th October 2008, on the A66 eastbound main carriageway from Hartington Interchange to Middlehaven Interchange, also Hartington entry slip and Marton Road exit and entry slips.
NEWPORT BRIDGE
The bridge will be closed for maintenance works on Sunday 26th October and Sunday 2nd November 2008. Traffic management will be in place from 07.00hrs until 19.00hrs and diversions will be in place via the A66 and A19. However, access for pedestrians/ cyclists and Emergency Vehicles will be maintained.
NEWPORT ROUNDABOUT
Lane closures on all approach roads to Newport Roundabout will be in place when required until mid December 2008, as part of the North Middlesbrough Accessibility Scheme. Delays will be expected.
ACKLAM ROAD ROUNDABOUT
Lumsden and Carroll Construction Ltd, will continue works until December 2008 to construct a new roundabout on Acklam Road, at the junction of Springvale Terrace. Temporary traffic signals will be in operation until the end of November 2008.
ST. BARNABAS ROAD, LINTHORPE
A temporary road closure is in place at the junction with Linthorpe Road, for NGN works that commenced on Monday 13th October 2008. The closure will be in place for the duration of the works, which are expected to be complete by the end of November 2008.
BRIDGE STREET EAST - TEMPORARY ROAD CLOSURE
Works are continuing to reconstruct the carriageway and footways on Bridge Street East, from Queens Square to Gray Street. The development works will continue until December 2008 and although the road will be closed to vehicles, pedestrian access will be maintained throughout this period.
GUNNERGATE LANE, MARTON
NEDL diversion works have commenced in the footpath at the junction with Stokesley Road. The works will continue until 24th October 2008.
HIGHBURY AVENUE/ TOLLESBY ROAD JUNCTION
NGN are continuing works to replace a gas main on Highbury Road, at the side of no. 62 Tollesby Road. The works will continue until 20th October 2008.
NEWHAM AVENUE/ TOLLESBY ROAD JUNCTION
NGN are continuing works to replace a gas main on Newham Avenue, at the side of no. 52 Tollesby Road. The work will continue until 20th October 2008.
CAVENDISH ROAD, BEECHWOOD
NWL works commenced on 6th October at the junction with Marton Way. The works will take place within the footpath and are expected to continue until 14th November 2008.
BRIDGE STREET WEST TO ZETLAND ROAD UNDERPASS
A temporary footpath closure will be in place until 20th October 2008, to allow bridge maintenance works to be carried out safely.
STREET LIGHTING MAINTENANCE WORKS
The general maintenance of street lighting columns is continuously ongoing at various locations in Middlesbrough.
RESURFACING WORKS
LATHAM ROAD, LINTHORPE
Carriageway resurfacing works, involving a temporary road closure, are continuing at the above location.
BRECKON HILL ROAD
Carriageway resurfacing is scheduled to take place on 27th October 2008.
ROMAN ROAD, LINTHORPE
Carriageway resurfacing is scheduled to take place on 27th October 2008.
FAKENHAM ROAD, WHINNEY BANKS
Carriageway resurfacing is scheduled to take place on 27th October 2008.
FOOTPATH WORKS
FULBECK ROAD NO'S 165-171
Works are scheduled to take place on 20th October 2008 to install knee rail to grass verge to stop vehicle trespass.
RAINSFORD CRESCENT
Works are scheduled to take place on 20th October 2008 to replace grass verges with tarmac at the above location.
AMPLEFORTH ROAD
Works commenced on 14th October 2008 to install disabled crossings at various locations.
MOORTOWN ROAD, BEECHWOOD
Works are ongoing to replace grass verges with paving at the above location.
MALLOWDALE, NUNTHORPE
Footpath resurfacing works are ongoing between Stainton Way and Clevegate.
MARTON ROAD
Footpath renewal works are continuing between St. Joseph's School and Belle Vue Grove Roundabout.


You can now post local community news directly to this website! Find out more
Keep up to date with TS10 Redcar subscribe to our RSS feed

easyAds123 - buying or selling? Search through 100s of ads for the best deals on Teesside
Leave a comment