A66 ROADWORKS
NORTH MIDDLESBROUGH ACCESSIBILITY SCHEME
Following completion of resurfacing works on the westbound carriageway by 17/12/08 there will be no further lane restrictions until after the Christmas period along this section of the A66. The 30mph speed limit needs to remain in place in both sections due to the temporary nature of the footbridge safety barriers and the safety of all road users. Further work will commence requiring lane restrictions in the New Year.
Further information will be available on www.northmiddlesbroughaccessibility.com
SLIP ROAD CLOSURE - NEWPORT INTERCHANGE
The slip road from Newport Roundabout onto the A66 eastbound, was closed in November 2008 for approximately 4 months, to enable the progression of works associated with the North Middlesbrough Accessibility Scheme. Diversions will be via Newport Road and Hartington Interchange. Traffic is being encouraged through signage to use the A19 flyover and A66 rather than Newport Bridge, to ease pressure on the diversion route.
A66 MAINTENANCE WORKS
Lane closures are necessary each Sunday at various locations on the A66 for detailed inspection works, gully cleaning, repairs to street lighting etc.
Maintenance works will not be carried out during the Christmas period but will commence again on Sunday 11/01/09.
MAJOR WORKS/ TEMPORARY CLOSURES
WINDWARD WAY/ BRIDGE STREET EAST JUNCTION - TEMPORARY CLOSURE
Works are nearing completion and the junction will be re-opened to traffic on Monday 15/12/08.
BRIDGE STREET EAST - TEMPORARY ROAD CLOSURE
Works are continuing to reconstruct the carriageway and footways on Bridge Street East, from Queens Square to Gray Street. The development works will continue until February 2009 and although the road will be closed to vehicles, pedestrian access will be maintained throughout.
ACKLAM ROAD ROUNDABOUT
Lumsden and Carroll Construction Ltd, will continue works until January 2009 to construct a new roundabout on Acklam Road, at the junction of Springvale Terrace. Temporary traffic signals will be in operation until Christmas 2008.
MINOR WORKS
DIXON'S BANK, MARTON
NWL are continuing repairs works between the junctions with Stainton Way and Guisborough Road, at the rear of 20 Darnbrook Way, until 19/12/08. Temporary traffic lights will be in operation.
DIXON'S BANK, MARTON
The proposed loop cutting work by Diamond Northern, between the junctions with Stainton Way and Guisborough Road, will be postponed to avoid conflicting with NWL works at that location.
The loop cutting will go ahead when NWL works are completed on 19/12/08.
PARK AVENUE NORTH, ORMESBY
NGN works commenced on 01/12/08 to replace a cast iron main in the footpath from the junction with Cargo Fleet Lane to o/s no 20. The works will continue until 02/01/09.
PARK AVENUE SOUTH, ORMESBY
NGN works commenced on 01/12/08 to replace a cast iron main in the footpath from the junction with Cargo Fleet Lane to o/s no 20. The works will continue until 31/12/08.
STOKESLEY ROAD, NUNTHORPE
NGN works commenced on 01/12/08 to replace 120m of gas main in the footpath from no. 20 Stokesley Road to the junction with Grey Towers Drive. Traffic management will be in operation with the use of temporary traffic lights. The works have been extended and will continue until 15/12/08.
CARISBROOKE AVENUE, THORNTREE
NGN works are continuing to renew the mains along the full length of the road. The works have been extended and will continue until 15/12/08.
SHREWSBURY ROAD, THORNTREE
NGN works are continuing to renew the mains between no's 1 and 23. The works have been extended and will continue until 29/12/08.
BIRKHALL ROAD, THORNTREE
NGN works commenced on 01/12/08 to renew the mains between the junction with The Greenway and no. 38. The works will continue until 23/12/08.
STREET LIGHTING MAINTENANCE WORKS
The general maintenance of street lighting columns is continuously ongoing at various locations in Middlesbrough.
FOOTPATH WORKS
CARGO FLEET ROAD, MIDDLEHAVEN
Resurfacing works are scheduled to begin during the week commencing 15/12/08.
PINEWOOD ROAD AREA, MARTON
Footpath resurfacing works are ongoing at the above location.
GLENEAGLES ROAD, BEECHWOOD
Works are ongoing to replace grass verges at the above location.
MALVERN DRIVE, BROOKFIELD
Works are ongoing to refurbish of footpaths at the above location, including a concrete strip for vehicle trespass.
HOYLAKE ROAD, BEECHWOOD
Works are ongoing to replace grass verges in certain areas.
MOORTOWN ROAD, BEECHWOOD
Works are ongoing to replace grass verges with paving at the above location.
MARTON ROAD
Footpath renewal works between St. Joseph's School and Belle Vue Grove Roundabout have been suspended until after the Christmas period.


You can now post local community news directly to this website! Find out more
Keep up to date with TS10 Redcar subscribe to our RSS feed

easyAds123 - buying or selling? Search through 100s of ads for the best deals on Teesside
Leave a comment...
Sign In